The City’s annual street repair and resurfacing project will begin in late July and is estimated to be completed by late December. Construction work hours are Monday through Friday, from 8:00 a.m. to 5:00 p.m. The repair will take place in several phases, and not all on the same day. Curb and gutter will be removed and replaced in a few places, then areas of poor pavement will be patched, then the edges of the street will be ground down, then cracks will be filled, then the street will be paved, then any traffic markings will be replaced. During construction, motorists will experience minor disruptions in traffic, temporary loss of parking spaces, temporary restricted street access, as well as an increase in noise and dust levels. Bus stop access will be maintained throughout the project.