City is still seeking funding for this project. Schedule will be determined once the City has funding to complete the project.
2016: Applied for project funding in TIGER grant. Unsuccessful.
2020: Considered applying for Active Transportation Program (ATP) Cycle 5 funding, developed concept plan and began outreach. Determined not to apply, given lack of matching funds and grant funding priorities.
April 2022: Council accepted 2022 Grant Priorities list, which included Stargell project, as part of the Annual Transportation Report.
June 2022: City applied for state and regional ATP Cycle 6 grant funding, but was unsuccessful.
June 2024: City will apply for state and regional ATP Cycle 7 grant funding, at the encouragement of grant fundors.