The Bay Farm Island Adaptation Project will reduce current flood risk and prepare the Bay Farm Island northern shoreline for up to two feet of sea level rise, which is expected to occur around 2040-2060. The project combines coastal flood protection, drainage improvements, habitat enhancements, and public access improvements. This is a near-term adaptation project that also lays the foundation for longer-term shoreline adaptation through the Alameda Shoreline Adaptation Plan, currently in development.
Bay Farm Island Adaptation Project Fact Sheet(PDF, 564KB)
Materials(PDF, 7MB) from Sept. 2025 Sea Level Rise Planning Fair covering Near-term Alternatives, Mid- to Long-term Considerations and the Near-term Adaptation Project for Bay Farm Island.
To remove the lagoon area of Bay Farm Island from the FEMA 100-year floodplain; protect against near-term sea level rise; bolster the northern shoreline and Bay Trail from erosion; enhance shoreline habitat with nature-based solutions; enhance public recreation, including improvements to the San Francisco Bay Trail.
Bay Farm Island's northern shoreline for the near-term project and the entire Bay Farm Island for the long-term strategy, in concert with the Alameda Shoreline Adaptation Plan.
Portions of Bay Farm Island currently sit within FEMA’s mapped Special Flood Hazard Area and the northern shoreline already floods during major coastal storms and King Tides. Flooding is expected to become more frequent and severe as sea levels and groundwater rise and extreme rainfall events intensify.
City Council endorsed the Bay Farm Island Adaptation Project design concept(PDF, 8MB) in January 2025.
Refined 30% design concepts(PDF, 111MB) were completed in April 2026.
Key Project Components
Coastal Flood Protection: Reduce coastal flood risk and remove homes from the FEMA Special Flood Hazard Area with new levee from Veterans Court to the lagoon.
Lagoon Flood Management Improve drainage and manage flooding during high Bay water levels with a new tide gate, pump station, and gravity pipe.
Nature-Based Shoreline & Habitat Enhancement Reduce erosion and enhance habitat with pocket beaches, rock islets, marsh improvements, sediment retention features, and native shoreline planting.
Veterans Court Reconfiguration Expand marsh and mudflat habitat while reconfiguring the roadway and parking area at Veterans Court.
Public Access & Recreation Improve the Bay Trail and shoreline experience with overlooks, seating, accessible shoreline access, a fishing pier, and educational signage.
Island Drive Adaptation Raise low areas along Island Drive to reduce flood risk and complete the near-term flood protection system.
Phase
Funding Source
Timeframe
Description
Phase 1: 30% design
FEMA Community Project
2023-2025
Phase 2: Refined 30% design
City General Fund
2025-2026
Phase 3: 60% design
State Coastal Conservancy Prop 68 grant
2026-2028
Phase 4: 100% Design and Construction
To be determined
2028-
2027 (estimated schedule)
2026
2025
2024
2023
2022
2021
2020
2019
Community Workshop - Presentation boards(PDF, 7MB) (September 2025)
Bay Farm Island Draft Concept Designs Workshop Presentation and Recording (December 2024)
Community Workshop Presentation, Recording, and Survey Results(PDF, 213KB) (May 2024)
Community Partner Engagement Strategy(PDF, 4MB) (March 2024)
OAAC FEMA BRIC Grant Application - Technical Report(PDF, 8MB) (February 2024)
Existing Conditions Report(PDF, 22MB) (February 2024)
OAAC ADAPT Sea Level Rise Criteria(PDF, 4MB) (January 2024)
OAAC King Tides Site Walk Project Overview Presentation(PDF, 19MB) (January 2024)
Erosion of the Bay Farm Island northern shoreline occurred during winter storms in 2024 at three locations shown in the map below: behind the Harbor Bay Club tennis court, behind 2905 Sea View Parkway, and behind 2857 Sea View Parkway.
In 2025, the City began seeking permits from the Bay Conservation Development Commission (BCDC), SF Regional Water Quality Control Board and the U.S. Army Corps of Engineers to install temporary tiger dams to protect these areas of the shoreline from further erosion. Permits have been issued by BCDC and the Regional Water Control Board, but the City continues to coordinate with the U.S. Army Corps of Engineers to get receive permit for complete these temporary measures.
The City is aware of the uneven surface and overall condition of the Wooden Bridge and recognize its importance as a key pedestrian and bicycle connection. The City Council recently allocated funding to design and implement a near-term rehabilitation project that will extend the bridge's service life and provide a safe, comfortable crossing for approximately the next 10 years. The City is working closely with the East Bay Regional Park District (EBRPD) on the project. For the longer term, the City secured a $500,000 grant which will partially fund a feasibility study for a future bridge replacement, and also applied for a second grant to cover the remaining project need. The feasibility study is expected to begin in Summer 2027.
Danielle Mieler, Sustainability and Resilience Manager
(510) 747-4713
dmieler@alamedaca.gov
If you need an alternative or translated format, please contact ada@alamedaca.gov.
Subscribe to our mailing lists for project updates under Climate Resiliency and Adaptation:
Subscribe
City Council endorsed the design concept on January 21, 2025. The City staff/CMG consultant team has completed 30 percent design. A Prop 68 grant, which is administered by the California Coastal Conservancy, will complete 60 percent design and environmental documentation in 2028.